Instance Build SLAs

Task Owner SLA
# Days from previous event
Estimated Working Days
From Start of Build
Example Days of Week
Instance Build Begins Intelitics - - Wed.
Week 1
Start Setting up Client tracking Intelitics 1 1 Thu.
Week 1
1st Round DNS Verification Records Delivered Intelitics 1 2 Fri.
Week 1
1st Round DNS Verification Records Successfully Placed Client 2 4 Tue.
Week 1
1st Round DNS Verified Intelitics 0 4 Tue.
Week 2
2nd Round DNS Records Delivered Intelitics 1 5 Wed.
Week 2
2nd Round DNS Records Successfully Placed Client 2 7 Fri.
Week 2
2nd Round DNS Verified Intelitics 0 7 Fri.
Week 2
Instance Final Testing (Started) Intelitics 1 8 Mon.
Week 2
Instance Administrator Login Delivered Intelitics 2 10 Wed.
Week 3
  • SLAs are based on completion of previous events. If a Client misses a timeline, we will not expedite any future SLAs to get back on track.
    • Eg. If Client takes 3 days to successfully place 1st round DNS records (normally 2 day SLA) then the timeline of all subsequent events are pushed back by one (1) day.
  • Items completed quicker than SLAs do not “shorten” the timeline. SLAs remain unchanged.